Full-cycle industrial compressor replacement completed at a bakery in Gilroy without production downtime

Bakery — Refrigeration Restoration Project (Completed)
ABC Service
We recently completed a major commercial refrigeration restoration project for Bakery in Gilroy, CA. The facility operates two rooftop condensers connected to a total of six evaporator units. One of the systems was fully non-operational, and both required deep cleaning and component replacement due to contamination and moisture.
System Overview
- 2 rooftop condensers
- 6 evaporators (3 per system)
- Left system: completely down
- Right system: running, but with noise and performance issues
- Findings: contamination, moisture, degraded oil, and failing TXVs and compressors
Work Completed
Step 1 — Full System Cleaning
We began with the non-operational left system:
- Removed TXV
- Performed a full chemical flush of the refrigeration circuit
- Eliminated contaminants, moisture, and old mineral oil
- Prepared lines for new components
Step 2 — TXV & Compressor Replacement
- Installed a brand-new compressor
- Installed a new TXV valve
- Pulled a deep 24-hour vacuum to ensure the system was completely moisture-free
Step 3 — Vacuum Check, Nitrogen Purge, Refrigerant Charge
- Verified vacuum hold
- Performed nitrogen pressure test and purge
- Charged the system with fresh refrigerant (provided by customer)
- Completed startup and operational testing
The same multi-day process was repeated for the right system. If leaks were detected, additional diagnostic and repair time was performed as needed.
Project Goals
- Restore full system functionality
- Improve reliability and cooling performance
- Protect equipment from oil contamination and moisture damage
- Extend lifespan of both refrigeration systems through replacement of critical components
Cost Summary
Total labor cost: under $20K
Includes:
- ✔ Full flushing of both systems
- ✔ Compressor replacements
- ✔ TXV replacements (all six units)
- ✔ 24-hour vacuum
- ✔ Nitrogen purge
- ✔ System charging and startup
Materials (compressors, TXVs, refrigerant, chemicals) — not included in labor and billed separately.